NPO Passat is preparing for the next launch of equipment at Petrikovsky GOK, which is scheduled for the second half of June. The mother solution systems are filled with water. The launch will equipment without load. Specialists of the chemical-technological department, service department, welder brigade will accompany the launch of the 2nd, 3rd and 5th sections of the factory. NPO Passat team live in Petrikov since the final stage of the construction of the processing plant.
We remind you processing plant in Petrikov is the largest investment project of Belaruskali, JSC. Investments - 1.5 billion dollars. The design capacity is 1.5 million tons of potash fertilizers. By 2025, it is planned that the plant’s capacity will be 3 million tons of potassium chloride per year. The reserves of the deposit will last for 120 years.